Delhi EFC approves revised hospital project costs; directs vigilance probe in arbitration award

Follow Us :
Text Size:

New Delhi, Aug 5 (PTI) The Expenditure Finance Committee (EFC) of the Delhi government, headed by Chief Minister Rekha Gupta, has approved revised funding estimates for hospital projects and directed a vigilance investigation into the payment of an arbitration award of Rs 94 crore related to the LNJP Hospital, officials said on Wednesday.

In its recent meeting, the EFC recommended proposals from the health department to increase the cost of constructing a new block at Lok Nayak Hospital from Rs 533.91 crore to Rs 1,268.85 crore. This revised estimate will be presented to the cabinet for approval.

The committee ordered a vigilance enquiry into the handling of the arbitration award in the case of LNJP hospital, which it identified as one of the major reasons for the increase in the project’s cost.

Additionally, the EFC approved revised estimates for the Madipur and Jwalapuri hospital projects, according to officials.

The health department has been asked to submit a detailed report on the arbitration award, examine whether any FIR had been registered against the previous contractor and obtain the latest status on investigations by the Vigilance Department and the Anti-Corruption Branch (ACB) related to the hospital projects.

The revised proposal for the LNJP Hospital project will now be placed before the council of ministers.

According to an official document, the project was approved in 2019 at an estimated cost of Rs 533.91 crore to build a double-basement, 22-storey block for medicine, maternity and advanced paediatric services, adding 1,570 beds to the hospital.

The health department said construction was progressing until a dispute arose over contractual conditions and payment for structural steel work. The contractor invoked the dispute resolution process under the contract and was later granted an arbitration award.

According to the department, the contractor then approached the Delhi High Court for implementation of the award, following which the amount was released, and the court attached the accounts of the PWD Health Zone to recover it.

The department informed the committee that Rs 586.09 crore had already been spent and the project was 55 per cent complete. It said the revised estimate of Rs 1,268.85 crore, including Rs 682.75 crore needed to complete the remaining work, was due to the arbitration award, the increase in GST from 12 per cent to 18 per cent, higher material and labour costs and changes made to hospital services after the COVID-19 pandemic.

The committee noted that the arbitration award amounted to Rs 94.61 crore, including Rs 82.44 crore as the award amount and Rs 12.17 crore as interest.

It asked the department to submit a detailed report explaining how the dispute arose, the sequence of events, the opinion of the law department, the basis of the award, its financial impact and the approvals given at different stages.

It said the vigilance enquiry should examine how the arbitration award was accepted and the payment released, whether prescribed procedures were followed and whether there were any lapses. The committee said responsibility should be fixed if any irregularities are found.

The committee also asked the health department to examine whether any FIR had been registered against the previous contractor. If one has been registered, and procurement rules allow, the department should evaluate whether the contractor can be barred from participating in new tenders for the remaining work, it said.

The revised proposal estimates that the remaining work on the hospital project will take 30 months to complete, including six months for planning and 24 months for execution.

In the same meeting, the EFC approved and sanctioned a revised estimate of Rs 466.50 crore for the 691-bed Madipur Hospital project, including Rs 203.60 crore for the remaining work.

The health department said the project is 65 per cent complete and the revised cost was due to the addition of two floors, the increase in GST, higher material and labour costs and changes made after the COVID-19 pandemic.

The committee also approved and sanctioned a revised estimate of Rs 484.04 crore for the Jwalapuri Hospital project, including Rs 223.53 crore for the remaining work. The health department said this project is also 65 per cent complete and cited similar reasons for the revised estimate. PTI SGV VIT MPL MPL

This report is auto-generated from PTI news service. ThePrint holds no responsibility for its content.

Subscribe to our channels on YouTube, Telegram & WhatsApp

Nine Years, Made Possible by Readers

In 2017, Shekhar Gupta started ThePrint with a simple belief: Indian readers want journalism that asks why and what next, not just what. And that enough of them would be willing to pay for good journalism.

Nine years on, that belief has held.

And, in these nine years, we’ve stayed true to our mission. We’ve been asking the follow-up questions, going beyond the headlines and explaining what’s actually happening. We’ve travelled across the country to bring you in-depth, visually-compelling stories from the ground.

It’s been nine years of readers choosing to make this possible. If you’d like to be one of them:

Support ThePrint

  • Tags

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Most Popular