scorecardresearch
Saturday, April 20, 2024
Support Our Journalism
HomeIndia44 Vande Bharat trains could be ready only by 2027, much later...

44 Vande Bharat trains could be ready only by 2027, much later than planned 2022 deadline

According to coach manufacturer ICF’s estimates, the whole process to roll out these 44 Vande Bharat train sets could take up to 78 months to complete.

Follow Us :
Text Size:

New Delhi: The Indian Railways has so far maintained that the planned 44 train sets (also called rakes) of Vande Bharat Express will be introduced in 2021-22, but an internal estimate by the Integral Coach Factory (ICF) shows that this could take six-and-a-half years to roll out.

In a letter to the Railway Board dated 14 July, the ICF, which manufactures rail coaches for India, said it would take 28 months to introduce the prototype rakes into commercial service. Additionally, it would take six months to start the series production, and subsequently, the supply of series equipment of each of the 44 rakes would take one month each.

In total, the whole process would thus take up to 78 months to complete, according to the ICF’s estimates. ThePrint has seen the letter.

This puts the estimated date for the rollout of all these train sets at 2027.

Sources told ThePrint that even though earlier this month, the Railway Board told the Prime Minister’s Office that the rest of the 44 trains will be completed in two years, it is next to “impossible” to achieve this target.

“It is a morale booster for the ICF to be picked for the production of these trains over any other global player, but it is next to impossible to achieve the two year target … Even the ICF timeline is a conservative estimate,” an official said on condition of anonymity.

Railway Ministry spokesperson D.J. Narain said the Railways is working according to the schedule, and they cannot comment unless they see the ICF letter.


Also read: Railway Board to now have a special cell to attract more investment, increase FDI inflow


Vande Bharat train sets

The original version of Vande Bharat rakes — also called the T-18 trains — had taken just 18 months to cover the stages of conceptualisation, design, manufacture and rollout, and two of these rakes — built at a cost of approximately Rs 100 crore — have been providing trouble-free service on two routes: Delhi-Varanasi and Delhi-Katra.

However, the production of the rest of the 44 rakes has been mired in controversy.

The project has also faced delays since the earlier proposal to import the complete train sets from foreign manufacturers had led to opposition from political parties, senior officials and other stakeholders, who had criticised the Railways for going global when there was indigenous technology in-house.

The turf war between the mechanical and the electrical engineering departments had resulted in allegations of favouritism, safety compromises and other flaws, which, in turn, led to the transfer of top officials from the team.

As a result, there have been several delays in the project, with the latest being the third tender floated by the government in December 2019 with changes meant to create a level-playing field to bring down prices.


Also read: Railways plan to introduce contactless ticketing with QR codes on handheld devices


 

Subscribe to our channels on YouTube, Telegram & WhatsApp

Support Our Journalism

India needs fair, non-hyphenated and questioning journalism, packed with on-ground reporting. ThePrint – with exceptional reporters, columnists and editors – is doing just that.

Sustaining this needs support from wonderful readers like you.

Whether you live in India or overseas, you can take a paid subscription by clicking here.

Support Our Journalism

3 COMMENTS

  1. This issue is very confusing. When acceptable Indian design and technology is available (and this is indeed a matter of pride and achievement for the Indian Railways), why there is a need to look for foreign sources? If there are technical issues like safety etc, they could be sorted out in due course. If cost is the issue, it could as well be brought down by increased production and possibly by exports to other countries. Piyush Goel has miserably failed to sort out this issue for a long time and it required intervention from PMO is a sad commentary on the state of affairs in the Railways, particularly when the trains produced have been giving excellent service on two routes. Piyus is doing a good job but this issue is his failure. He must sort this out immediately.

    • Dont trust the print. They love spreading false news against Modi government. Most of the sources here tell that it will be ready by 2022-2023.

  2. This is Very bad for country’s development, project run as snail speed, totally waste…..
    & this is required in 3 years not 7,fulfill country ‘s requirements.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Most Popular