New Delhi, Mar 24 (PTI) The Committee on Public Accounts has questioned the Railway Ministry for the delay in giving approval to a detailed project report for creating a passenger terminal at Parel in Mumbai.

It also noted that the ministry failed to adhere to its norms in setting up a coach refurbishment unit at Parel Workshop in Central Railway which incurred an undesirable expenditure of Rs 22.07 crore, after which it decided to create a passenger terminal.

A report tabled in the Parliament on March 21, the Committee noted that the Ministry’s norms (issued in August 1980 and February 1985) said that before calling tenders all zonal railways should ensure that they are in a position to handover the site of work and supply plan to the contractor.

In 2007-08, the Central Railways sanctioned the work to set up a Mid-Life Rehabilitation facilities (coach refurbishment facilities) of 25 broad gauge coaches every month at an anticipated cost of Rs 30.24 crore.

It awarded contract for civil work to Unity Construction, Mumbai in February 2010 at a cost of Rs 6.89 crore with completion period of 18 months, however, due to non-availability of funds and non-providing of site etc, it was foreclosed in March 2014 after an expenditure of Rs 4.58 crore.

The Committee noted that the Railways awarded another contract to complete leftover civil work to Pruthivi Construction, Mumbai for Rs 5.94 crore with completion period of 12 months. However, due to reasons such as non-handing over of site, the contract was extended till March, 2018 and later foreclosed.

The Railways, then, decided to close Parel Workshop and create a Passenger Terminal facility for which a detailed project report sent to the Ministry of Railways on February 24, 2020 has been still pending.

“Thus, non-adherence to the Ministry of Railways’ instructions for providing clear site of work before calling for tenders, rendered the expenditure of Rs 22.07 crore incurred on the creation of MLR, as infructuous,” the report said.

“Besides, the proposal of GM/Central Railway for creation of passenger terminal by closing Parel Workshop despite incurring expenditure of Rs 22.07 crore on MLR indicated poor planning and imprudence,” it added.

The Ministry submitted that due diligence would be taken to ensure that the sites are available for carrying out the work before calling tender in future.

“The Committee are perturbed to note that the Action Taken Note submitted by the Ministry failed to explain the rationale of awarding of the remaining civil work of the MLR Project to a new contractor (Pruthivi Construction) in January, 2015 when the original contract awarded in February, 2010 with a target period of 18 months was already running on extended period,” the report said.

Regarding the Passenger Terminal Facility, the Committee asked the Ministry to apprise it as to whether all aspects of handling trains required for the Passenger Terminal have been worked out.

“The Committee would also like to be apprised of the status of the Planning of the Phase-I work of Parel Terminus. The Committee would like to be apprised of the reasons for inordinate delay in the DPR approval process and the efforts made by Railways for drawing up a time-table for DPR clearance at various levels,” the report said. PTI JP NB

This report is auto-generated from PTI news service. ThePrint holds no responsibility for its content.

Subscribe to our channels on YouTube, Telegram & WhatsApp

Support Our Journalism

India needs fair, non-hyphenated and questioning journalism, packed with on-ground reporting. ThePrint – with exceptional reporters, columnists and editors – is doing just that.

Sustaining this needs support from wonderful readers like you.

Whether you live in India or overseas, you can take a paid subscription by clicking here.

Support Our Journalism

  • Tags

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Most Popular