HomeIndiaElectric trains to begin operations in Tripura by February

Electric trains to begin operations in Tripura by February

Launched in 2022, the Rs 46 crore electrification project includes establishment of 3 traction power substations that are likely to be completed by next month.

Follow Us :
Text Size:

Agartala: Trains running on electricity are likely to begin operations in Tripura by February this year, with the completion of a key electrification project in the northeastern state, officials said on Monday.

The state at present has diesel-powered train engines. The Rs 46-crore electrification project, which was launched in 2022, will connect Tripura with the national railway grid.

The Tripura State Electricity Corporation Ltd (TSECL) will be ready to supply power to the electric transmission line of the Railways in the state by February, the officials said.

The North Eastern Railways (NFR) has already completed electrification work from Badarpur to Agartala via Dharmanagar in the northeastern state.

“We had undertaken work for erection of three traction power substations – Kumarghat in Unakoti district, Teliamura in Khowai district and Udaipur in Gomati district. The erection of Kumarghat substation was completed in March last year,” Assistant General Manager (Transmission), TSECL, Nirupam Guha, told PTI.

He said the substation at Udaipur is set to be completed by this month and the one at Teliamura by February.

“After the completion of the three traction substations, the TSECL will be ready in all respects to energise the railway electric transmission line from Dharmanagar to Agartala and elsewhere,” Guha said.

Guha said the Railways has sought 5 MW power for each substation on a daily basis, and if required, more power could be supplied.

“We are confident once this project is completed, more advanced and faster trains will be introduced in the northeastern state. It will play a crucial role in boosting infrastructure and the economic growth of the state,” Guha said.

According to Kapinjal Kishore Sharma, Chief Public Relations Officer of NFR, the electrification work has been completed from Badarpur to Agartala via Dharmanagar, barring the hilly stretch of the Lumding-Badarpur section.

“Steps have been taken to complete the electrification work from Lumding to Agartala as early as possible,” he said.

This report is auto-generated from PTI news service. ThePrint holds no responsibility for its content.


Also read: Two railways privatisation models for India to learn from—UK & Japan


 

Subscribe to our channels on YouTube, Telegram & WhatsApp

Support Our Journalism

India needs fair, non-hyphenated and questioning journalism, packed with on-ground reporting. ThePrint – with exceptional reporters, columnists and editors – is doing just that.

Sustaining this needs support from wonderful readers like you.

Whether you live in India or overseas, you can take a paid subscription by clicking here.

Support Our Journalism

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Most Popular