HomeIndiaPetronet seeks up to 1 million metric tonnes per annum LNG under...

Petronet seeks up to 1 million metric tonnes per annum LNG under long-term Qatar deal

The gas importer is looking to expand the capacity of its LNG terminals by more than 53% in the coming years, including opening of its first terminal on the east coast.

Follow Us :
Text Size:

Bengaluru: India’s top gas importer Petronet LNG, will seek up to 1 million tonnes per annum (mtpa) of liquefied natural gas (LNG) when it renews its long-term deal with Qatar this year, the company’s chief executive said on Tuesday.

“We are seeking an additional 0.75 to 1 mtpa on top of existing 8.5 mtpa contact,” Chief Executive A.K. Singh told reporters on the sidelines of the Indian Energy Week conference.

Petronet, which is currently purchasing LNG from Qatar at $16 per million British thermal unit (mmbtu), has until the end of this year to renew its deal.

India’s LNG imports fell for the second straight year in 2022, mainly due to fewer imports by utilities as the country ramped up coal-fired power production at the expense of natural gas.

The energy-hungry nation expects deeper penetration of city gas distribution to drive LNG demand in the coming years.

Petronet, which is currently purchasing 1.42 mtpa of LNG from Exxon Mobil Corp’s Gorgon project in Australia, will receive an additional 0.6 mtpa under the deal from 2025-26, Singh said.

This, he added, would be in addition to the 2.02 mtpa it will import from Gorgon by 2025-26, although a timeline for the shipments has not been finalized yet.

The gas importer is looking to expand the capacity of its LNG terminals by more than 53% in the coming years, including by opening its first terminal on India’s east coast.

The state-run company currently owns a 17.5 mtpa LNG terminal in Dahej in the western state of Gujarat and a 5 mtpa capacity plant in Kochi in southern India. It is building its third terminal in Gopalpur in eastern the state of Odisha.

“We are looking for 12 million tonnes of additional LNG (capacity) – 3 for Kochi, 4 for Gopalpur and 5 mtpa for Dahej,” Singh said.

The Kochi terminal is currently running at a lower capacity as pipeline connectivity was not fully ready, he said.

(Reporting by Nidhi Verma; Writing by Sudarshan Varadhan; Editing by Sudipto Ganguly and Savio D’Souza)

Disclaimer: This report is auto generated from the Reuters news service. ThePrint holds no responsibilty for its content.

 


Also read: Sarbananda Sonowal, Jassim Saif Ahmed Al-Sulaiti discuss strengthening India-Qatar maritime cooperation


 

Subscribe to our channels on YouTube, Telegram & WhatsApp

Support Our Journalism

India needs fair, non-hyphenated and questioning journalism, packed with on-ground reporting. ThePrint – with exceptional reporters, columnists and editors – is doing just that.

Sustaining this needs support from wonderful readers like you.

Whether you live in India or overseas, you can take a paid subscription by clicking here.

Support Our Journalism

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Most Popular